Gujarat Solar/Wind Hybrid RE PARK (30 GW)

30 GW Hybrid Renewable Energy Park, Kutch, Gujarat. As on 15-06-2021

Project Status

  • Under Govt waste land policy a large scale 30 GW RE Park is identified at Vighakot BSF Post, near International Border in Kutch district.
  • Approx. 72,400 ha land for 27,700 MW RE capacity has been allotted to 6 Developers.
  • Developers have to develop 50% of capacity in 3 years and 100 % capacity in 5 years from completion of new approach road i.e 31.12.2021.
Sr.NoName of Park DevelopersSolar-Wind Hybrid capacity (MW)Allocated Land in (Ha.)
1Gujarat Industrial Power Company Limited (GIPCL)23754750
2Gujarat State Electricity Corporation Limited (GSECL)33256650
3National Thermal Power Corporation Limited (NTPC)47509500
4Adani Green Energy Limited (AGEL)950019000
5Sarjan Realities Limited (SRL)47509500
6Solar Energy Corporation of India Limited (SECI)3000 (only wind)23000
Total27700 MW 72400 Ha
  • Construction of New Approach road (16.26 KM) and widening & Strengthening of existing road (Approx 40.83 KM) is started and planned to be commissioned by 31st Dec.,2021. Work orders issued and work on site under progress
  • Power Evacuation & Transmission system has been planned by CEA and CTU (PGCIL). Location study & route survey is started. Tenders are invited. However, for actual execution of transmission scheme, developers have to submit applications to CTU for connectivity and Long Term Open Access (LTA) and enter into contract with CTU for the same
  • State Govt. has reserved 300 ha. land for 3 pooling sub stations ( Approx. 10 GW each ).
  • A provision of requisite (1500 Mtrs) Right of way for transmission lines along the road within park is also made.
  • To meet the water requirement, developers shall establish Brackish groundwater desalination plants within their park area.
  • Construction power shall be provided by DISCOM ( PGVCL) on application by Developers and Payment of applicable charges