Top
Lignite projects

Ghogha -Surka Lignite Mining Project

Ghogha -Surka Lignite Mining Project :

Ghogha-Surka Lignite Mine covers an area of 1355 hectares and cover land of villages : Thordi, Surka, Rampar, Alarap of Bhavnagar Taluka and villages Badi, Hoidad , Padva and Malekvadar of Ghogha Taluka. The area lies between Latitudes: 210 26' 00 to 210 38' 45" N and Longitudes 720 11' 55" to 720 15' 00"E. This block is about 26 km away from Bhavnagar District Head quarter and 10 km from Ghogha Taluka. The site can be approached from Bhavnagar Transa and Bhavnagar- Koliyak Road.

Ghogha-Surka Lignite Mine is designed for production capacity @ 2.25 Million Tonne per Annum and is catering the fuel requirement of 500MW Bhavnagar Lignite Thermal Power Project.

The Ghogha-Surka Lignite Mine has received various mine safety awards and having NIL injury frequency rate.

Details:

Mining Lease Area1355 Hectaresr
Approved Mine Capacity2.25MTPA
Extractable Reserve of Lignite (MTe)54.68 Million Tonnes
Average Stripping Ratio1: 9.32
Commencement of Mining Operations 09.04.2018




Environment Clearance

Sr.No DetailsDownload
1Ghogha-Surka, Khadsaliya-I and Khadsaliya-II lignite mines in BhavnagarDownload 


Environment Compliance of EC

Sr.No DetailsDownload
1Six monthly Compliance Report for the period from Jan 2022 upto Jun 2022Download 
2Six monthly Compliance Report for the period from July 2021 upto December 2021Download 
3Six monthly Compliance Report for the period from January 2021 to June 2021Download 
4Six monthly Compliance Report for the period from July 2020 upto December 2020Download 
5Six monthly Compliance Report for the period from January 2020 upto June 2020Download 
6Six monthlyCompliance Report for the period from July 2019 upto December 2019Download 
7Six monthly Compliance Report for the period from January 2019 upto June 2019Download 
8Six monthly Compliance Report for the period from July 2018 upto December 2018Download 
9Six monthly Compliance Report for the period from January 2018 upto June 2018Download 
10Ghogha Surka Lignite Mine (2.25MTPA in 1355 hectares) and Khadsaliya-I (1MTPA in 711.4247 hectares) and Khadsaliya-II Lignite Mine (0.75 MTPA in 914.1492 hectares) of M/s/ GPCLDownload 


Environmental Statement (FORM-V) of EC

Sr.No DetailsDownload
1FORM-V - Environmental Statement of Ghogha-Surkha Lignite Mine - FY 2020-21Download 
2FORM-V - Environmental Statement of Ghogha-Surkha Lignite Mine - FY 2019-20Download 
3FORM-V - Environmental Statement of Ghogha-Surkha Lignite Mine - FY 2018-19Download 


Khadsaliya- I Lignite Mining Lease :

Khadsaliya-I Lignite Mine covers an area of hectares and covers land of villages Khadsaliya, Lakhanka and Thalsar of Bhavnagar Taluka and Morchand of Ghogha Taluka. It lie between Latitudes: 210 31' 25" to 210 33' 15" N and Longitudes 720 13' 30" to 720 14' 55" E.. This block is about 26 km away from Bhavnagar District Head quarter and 10 km from Ghogha Taluka. The site can be approached from Bhavnagar Somnath or Bhavnagar- Koliyak Road

Khadsaliya-I Lignite Mine is designed for production capacity @ 1.00 Million Tonne per Annum and will be catering the fuel requirement of 500MW Bhavnagar Lignite Thermal Power Project.

The mining activity is not started

Details:

Mining Lease Area711.4247 Hectares
Approved Mine Capacity1.00 MTPA
Mineable Reserve of Lignite (MTe)21.60
Average Stripping Ratio1: 8.81
Commencement of Mining Operations Not Started


Environment Clearance

Sr.No DetailsDownload
1Ghogha-Surka, Khadsaliya-I and Khadsaliya-II lignite mines in BhavnagarDownload 


Khadsaliya- II Lignite Mining Lease :

Khadsaliya-II Lignite Mine covers an area of 914.1492 hectares and covers land of villages Alapar, Bhadbhadiya, Hatav, Khadsaliya of Bhavnagar Taluka. It lie between Latitudes: 210 26' 00 to 210 38' 45" N and Longitudes 720 11' 55" to 720 15' 00"E. This block is about 29 km away from Bhavnagar District Head quarter and 12 km from Ghogha Taluka. The site can be approached from Bhavnagar -Transa or Bhavnagar- Koliyak Road.

Khadsaliya Lignite Mine is designed for production capacity @ 0.75 Million Tonne per Annum and will be catering the fuel requirement of 500MW Bhavnagar Lignite Thermal Power Project.

The Mining activity has not started.

Details:

Mining Lease Area914.1492 Hectares
Approved Mine Capacity0.75 MTPA
Extractable Reserve of Lignite (MTe)14.29 Million Tonne
Average Stripping Ratio1: 23.26
Commencement of Mining Operations Not Started


Environment Clearance

Sr.No DetailsDownload
1Ghogha-Surka, Khadsaliya-I and Khadsaliya-II lignite mines in BhavnagarDownload 
આ વિભાગમાં      



Gujarat Solar Rooftop Programme
-